Demolition of PJ Operation – pusher furnace chimney

Before the start of demolition work, the site was secured, i.e.: installation of mobile fencing and securing the surrounding premises against any damage caused by demolition rubble. With the aid of cranes that held the man basket with personnel and excavator, the chimney demolition commenced. The rubble was taken out of the chimney base opening and taken to the intermediate landfill. Following completion of the chimney demolition, the foundations were also broken up and backfilling with compaction was carried out. Finally, all construction site safety provisions were removed.