Demolition of house c.n. 1799 in Karviná-Mizerov

Demolition of reinforced concrete apartment building, which had 10 floors and of total height of approx. 30 m, was carried out. Prior to the work commencement, engineering networks were marked out and their disconnection and relocation took place. Subsequently, manual dismantling of house fittings, dismantling of WC cores, floors, windows, doors, lining and other technical equipment. Following machine demolition of the building, including demolition of the floor with continuous removal of rubble, the pit was filled with earth followed by the final landscaping and sowing of grass seed. The pertinent hardened areas were returned to their original condition by laying bitumen.