110/22 kV transformer substation Bohumín – External fencing

Work on this contract began with demolition of the existing fencing and public lighting. Subsequently, installation of new public lighting poles, new cabling and earthing took place. The construction of new fencing including earthing, whereas landscaping was carried out in phases. The wall required particular care as partial demolition of the brick fence, construction of a new section and rehabilitation of the existing brickwork had to be done. At the end of the construction, the required tests and technical audits were carried out.