Noise reduction measures at Trmice Heating Plant
The project objective was to reduce the existing acoustic load generated by Trmice Heating Plant. Work ranged from preparing production documentation for steel structures and acoustic enclosures, to electrical project, which included remote control to the control room and KKS codes. The actual realisation was carried out from the initial noise measurement, followed by the demolition of paved areas and existing structures that would clash with new structures, construction of new foundations to the supply and installation of steel structures. Acoustic panels were subsequently placed on these structures. The finishing works included electrical works – lighting, power supply sockets, installation of fans, commissioning the control room remote control and the final attenuation measurement.